Understanding that each project/process is unique, TFC staff takes the following approach:
- Meet with client to determine specific needs & concerns
- Create a customized checklist based on the client’s needs
- Assemble all information collected during the project’s planning, design & construction
- Sort project data from the Intelligent P&ID design database into the appropriate areas:
- Equipment
- Piping
- Valves
- Instrumentation
CHECK OUT:
Our team will perform a walk-down in addition to functionally testing of all valves in the the entire piping system.
Activities include:
- Confirm complete installation of all required parts
- Perform hydro test
- Perform pressure test
- Problem-solve all issues with gaskets, welds, & valves
MECHANICAL COMPLETION AUDITS & REPORTING
The audit includes such activities as:
- Confirm correct equipment installed
- Confirm correct installation procedure for each piece of equipment
- Check type & amount of lubrication
- Check rotation
Contact Details: